03. (40 Points). A ssume that the ePaint Store has its own manufacturing facility in which it produces Ironcoat paint. The ordering cost, Co, is the cost of setting up the production process to make pain Co=$140. Recall that Cc-s1.1 per gallon and D-22,000 gallons per y operates the same days the store is open (i.e. 311 days) and produces 160 gallons of paint per day. The lead time is 9 days. Determine the optimal order size, total inventory cost, the length of time to receive an order, the number of orders per year, the maximum inventory level, and reorder point. ear. The manufacturing facility

03. (40 Points). A ssume that the ePaint Store has its own manufacturing facility in which it produces Ironcoat paint. The ordering cost, Co, is the cost of setting up the production process to make pain Co=$140. Recall that Cc-s1.1 per gallon and D-22,000 gallons per y operates the same days the store is open (i.e. 311 days) and produces 160 gallons of paint per day. The lead time is 9 days. Determine the optimal order size, total inventory cost,