7. value: 1.36 points Conceptual Question 19-8 Which of the following statements is correct… Which of the following statements is correct with respect to slack time? OThe slack time of an activity is the latest completion time of the activity minus the earliest completion time. OThe slack time of an activity is the latest start time of the activity minus the earliest start time. OThe slack time of an activity determines by how much an activity can be delayed without impacting the overall completion of the project. OAll of these statements are correct.

7. value: 1.36 points Conceptual Question 19-8 Which of the following statements is correct… Which of the following statements is correct with respect to slack time? OThe slack time of an activity is the latest completion time of the activity minus the earliest completion time. OThe slack time of an activity is the latest start time of the activity minus the earliest start time. OThe slack time of an activity determines by how much an activity can be delayed without