8. Analyzing the critical path of a project provides which benefit? A. Identifies the fastest path to complete the project B. Displays work in a horizontal bar graph C. Identifies tasks for the work breakdown structure D. Prioritizes which activities to more closely manage 9. Using the critical path method for project management, the critical path should have… A. The most slack of any path in the project B. At least one unit (day/week/month etc.) of slack C. Zero slack D. Not enough information to finish the statement

8. Analyzing the critical path of a project provides which benefit? A. Identifies the fastest path to complete the project B. Displays work in a horizontal bar graph C. Identifies tasks for the work breakdown structure D. Prioritizes which activities to more closely manage

9. Using the critical path method for project management, the critical path should have… A. The most slack of any path in the project B. At least one unit (day/week/month etc.) of slack C. Zero slack D.