a. Create a Network Diagram b. Calculate ES, EF, LS, LF (Early Start, Early Finish, Late Start, Late Finish) c. Define the Critical Path d. How many weeks will the project take to complete? Immediate Weeks Predecessor 1.Activity

a. Create a Network Diagram b. Calculate ES, EF, LS, LF (Early Start, Early Finish, Late Start, Late Finish) c. Define the Critical Path d. How many weeks will the project take to complete? Immediate Weeks Predecessor 1.Activity

 

Solution

https://d2vlcm61l7u1fs.cloudfront.net/media%2Fe51%2Fe5108f0d-f53c-4c65-b2e7-9da0dc092d0b%2FphpOOetbA.png
b) Early start of A = 0

Early finish of A = early start + activity time

Early finish of A = 0 + 8 ( 8 weeks)

early start of B = 0

early finish of B = 0 + 8 ( 8 weeks)

early

AllEscortAllEscort