Capacity Planning Exercises 1. For the information below, develop rough cut capacity plan (RCCP) for the MPS using: (1) a rough cut using routings (capacity bills method, and (2) a resource profile method (offsetting by lead time) WEEK WEEK 200 WORK CENTER SETUP HOURS RUN HOURSAUIT LEAD TIME 201 302 Part X Part Y Part Z Part R 1 week 1 week 10 400 500 12 1.0 2 week) i week i week)

Capacity Planning Exercises 1. For the information below, develop rough cut capacity plan (RCCP) for the MPS using: (1) a rough cut using routings (capacity bills method, and (2) a resource profile method (offsetting by lead time) WEEK WEEK 200 WORK CENTER SETUP HOURS RUN HOURSAUIT LEAD TIME 201 302 Part X Part Y Part Z Part R 1 week 1 week 10 400 500 12 1.0 2 week) i week i week)

 