Complete the following MRP record. Initial inventory is zero for all parts. Safety stock is zero, and lead time is 1 period for all parts. Copy the MRP charts, and paste in the answer area. Complete the MRP records Bill of materials Period 1 2 3 4 5 Part M Gross Requirement 100 200 Lot size=200, Lead time=1, safety stock=0 Scheduled Receipts Projected Available Balance Planned Order Release Period 1 2 3 4 5 Part P Gross Requirement Lot for Lot, Lead time=1, safety stock=0 Scheduled Receipts Projected Available Balance Planned Order Release Period 1 2 3 4 5 Part Q Gross Requirement Lot for Lot, Lead time=1, safety stock=0 Scheduled Receipts Projected Available Balance Planned Order Release https://d2vlcm61l7u1fs.cloudfront.net/media%2F0de%2F0de94b68-c60d-4b2e-8be7-a414afd5765a%2FphpjhHPP4.png

Complete the following MRP record. Initial inventory is zero for all parts. Safety stock is zero, and lead time is 1 period for all parts.

Copy the MRP charts, and paste in the answer area. Complete the MRP records

Bill of materials

Period

1

2

3

4

5

Part M

Gross Requirement

100

200

Lot size=200, Lead time=1, safety stock=0

Scheduled Receipts

Projected Available Balance

Planned Order Release

Period

1

2

3

4

5

Part P

Gross Requirement

Lot for Lot, Lead time=1, safety stock=0

Scheduled Receipts

Projected Available Balance

Planned Order Release

Period

1

2

3

4

5

Part Q

Gross Requirement

Lot for Lot, Lead time=1, safety stock=0

Scheduled Receipts

Projected Available Balance

Planned Order Release