Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table Period 1 23 45 6 78 9 10 12 Gross requirements 30 30 40 70 20 10 70 60 “Holding cost= $3.50/unit/week; setup costs $200; lead time= 1 week; beginning inventory-40. Develop a lot-for-lot solution (enter your responses as whole numbers) Period 1 2 3 45 678 910 11 12 Gross requirements 30 30 40 70 20 10 70 60 On-hand at beginning