Flow units arrive at a rate of 10 units per hour. The arrival process is Poission. It takes, on average, 6 minutes to serve a flow unit. Service is provided by 4 servers. Incoming flow units will be lost when all servers are busy. (a) Implied utilization is (b) The probability that all servers are busy is (c) The actual flow rate is (Keep three decimal places. Hint: use the Erlang loss table.) units per hour. (Keep two decimal places.)

Flow units arrive at a rate of 10 units per hour. The arrival process is Poission. It takes, on average, 6 minutes to serve a flow unit. Service is provided by 4 servers. Incoming flow units will be lost when all servers are busy. (a) Implied utilization is (b) The probability that all servers are busy is (c) The actual flow rate is (Keep three decimal places. Hint: use the Erlang loss table.) units per hour. (Keep two decimal places.)

 

Solution