Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations were calculated. For Path 1-2-5 we have a Path Mean = 31 and a Path Standard Deviation = 3. For Path 1-3-4-5 we have a Path Mean = 27 and a Path Standard Deviation = 2. Determine both the Probability that Path 1-2-5 will finish in 31 Days or Less and the Probability that the Project will finish in 31 Days or Less. Question 5 options: 0.84134474 : 0.841148982 0.747507533 : 0.746498422 0.908788718 : 0.908759922 0.5 : 0.488624969

Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations were calculated. For Path 1-2-5 we have a Path Mean = 31 and a Path Standard Deviation = 3. For Path 1-3-4-5 we have a Path Mean = 27 and a Path Standard Deviation = 2. Determine both the Probability that Path 1-2-5 will finish in 31 Days or Less and the Probability that the