Given the following data, develop MRP tables and indicate the Planned order releases for all items. A is an MPS item. A needs 4 C’s and 2 F’s. Every C needs 6 F’s. Period 6 7 8 9 GR-A 0 0 2000 1500 On hand inventory for all items is 400 and lead time for A is 1 period, LT for F is 1 period and LT for C is 2 periods. Use lot-for-lot for A and a lot size of 900 or multiples of 900 for C and lot size of 2000 or multiples of 2000 for F. Draw the Bill of Material Fill up the Low level code Table Item Low level code A C F A 1 2 3 4 5 6 7 8 9 GR EI NR PO Receipt PO Release C 1 2 3 4 5 6 7 8 9 GR EI NR PO Receipt PO Release F 1 2 3 4 5 6 7 8 9 GR EI NR PO Receipt PO Release

Given the following data, develop MRP tables and indicate the Planned order releases for all items.

A is an MPS item. A needs 4 C’s and 2 F’s. Every C needs 6 F’s.

Period

6

7

8

9

GR-A

0

0

2000

1500

On hand inventory for all items is 400 and lead time for A is 1 period, LT for F is 1 period and LT for C is 2 periods. Use lot-for-lot for A and a lot size of 900 or multiples of 900 for C and lot size of