Homework: Problem Set 6 Score: 0 of 5 pts Problem E.19 Save 4 of 7 (3 complete) ▼ Hw Score: 32%, 8 of 25 pts Question Help Richard Dulski’s firm is about to bid on a new radar system. Although the product uses new technology, Dulski believes that a learning rate of 80% is appropriate. The first unit is expected to take 640 hours, and the contract is for 17 units a) The total amount of hours to build the 17 units 6174 hours (round your response to the nearest whole number). Enter your answer in the answer box and then click Check Answer.

Homework: Problem Set 6 Score: 0 of 5 pts Problem E.19 Save 4 of 7 (3 complete) ▼ Hw Score: 32%, 8 of 25 pts Question Help Richard Dulski’s firm is about to bid on a new radar system. Although the product uses new technology, Dulski believes that a learning rate of 80% is appropriate. The first unit is expected to take 640 hours, and the contract is for 17 units a) The total amount of hours to build the