If an interim deliverable is too late for the next successor deliverable, the best way for a project team to adjust the schedule to finish earlier is by:
a.
Increasing resources.
b.
Reworking the critical path.
c.
Decreasing the project scope.
d.
Creating concurrent deliverables.
e.
Negotiating deadlines with the project customer and/or project sponsor.
Solution