Please answer the following MCQ Here are the idle times for 4 activities of a project, which activity is on the critical path? a. Activity H, idle time 0 days b. Activity C, idle time 4 days c. Activity A, idle time 3 days d. Activity F, idle time 2 days

Please answer the following MCQ

Here are the idle times for 4 activities of a project, which activity is on the critical
path?
a. Activity H, idle time 0 days
b. Activity C, idle time 4 days
c. Activity A, idle time 3 days
d. Activity F, idle time 2 days

 

Solution

I am assuming all the activities are required for the completion of the project as no other information has been given/uploaded here.

Out of the 4 options, if all the 4 activities are involved in