Product A is an end item and is made from two units of B and three of C. B is made of two units of D and three of E. C is made of two units of F and one of E.
A has a lead time of one week. B, C, and E have lead times of two weeks, and D and F have lead times of three weeks.
b.
If 95 units of A are required in Week