Question 47 0.4 pts If each task (with the time each task takes to do given in minutes) in the continuously operating sequential process below is assigned to a different person (there are five workers in all, one for each task), which task is the bottleneck? 15 min 10 min 6min 20 min 9 min Task E Task D Task B O Task C Task A earch

Question 47 0.4 pts If each task (with the time each task takes to do given in minutes) in the continuously operating sequential process below is assigned to a different person (there are five workers in all, one for each task), which task is the bottleneck? 15 min 10 min 6min 20 min 9 min Task E Task D Task B O Task C Task A earch

 

Solution

Answer- Task D is bottleneck as it is taking highest time (20