Seven jobs must be processed in two operations: A and B. All seven jobs must go through A and B in that sequence—A first, then B. Determine the optimal order in which the jobs should be sequenced through the process using these times: Job Process A Time Process B Time Position in Sequence 1 8 9 2 7 5 3 9 9 4 7 7 5 2 3 6 3 2 7 5 5

Seven jobs must be processed in two operations: A and B. All seven jobs must go through A and B in that sequence—A first, then B.

Determine the optimal order in which the jobs should be sequenced through the process using these times:
Job Process A
Time Process B
Time Position in Sequence
1 8 9
2 7 5
3 9 9
4 7 7
5 2 3