Seven jobs must be processed in two operations: A and B. All seven jobs must go through A and B in that sequence—A first, then B. Determine the optimal order in which the jobs should be sequenced through the process using these times: Job Process A Time Process B Time Position in Sequence 1 9 8 2 6 6 3 8 5 4 7 6 5 2 3 6 1 2 7 3 4

Seven jobs must be processed in two operations: A and B. All seven jobs must go through A and B in that sequence—A first, then B.

Determine the optimal order in which the jobs should be sequenced through the process using these times:
Job Process A
Time Process B
Time Position in Sequence
1 9 8
2 6 6
3 8 5
4 7 6
5 2 3