The following table contains information regarding jobs that are to be scheduled through one machine. Assume jobs are listed in order of arrival (i.e., A, then B, then C, etc.). JOBPROCESSING TIME (DAYS)DUE DATE A7 20 B15 21 C1 16 D12 17 E11 15 F4 6 G5 12 a. What is the first-come, first-served (FCFS) schedule? Job Flow Time (Click to select)FEGBADC (Click to select)GEAFDCB (Click to select)BAEGFCD (Click to select)AGBFEDC (Click to select)DFBGECA (Click to select)EBFACGD (Click to select)DBCFGEA What is the shortest operating time (SOT) schedule? Job Flow Time (Click to select)CFAEDGB (Click to select)GECFDAB (Click to select)EFAGBCD (Click to select)EBAFGCD (Click to select)DBEAGFC (Click to select)AFCBGDE (Click to select)GEDBCAF c. What is the slack time remaining (STR) schedule? Job Flow Time (Click to select)CEFBDGA (Click to select)FDEGBCA (Click to select)GDCABEF (Click to select)BGCAEFD (Click to select)ACDBEFG (Click to select)GFEDACB (Click to select)ABCGDFE . What is the earliest due date (EDD) schedule? Job Flow Time (Click to select)EAGFDBC (Click to select)CFAGEBD (Click to select)FBDGEAC (Click to select)AFGDBEC (Click to select)EFDBGAC (Click to select)DACBEFG (Click to select)BCFGAED e. What are the mean flow times for each of the schedules above? (Round your answers to 1 decimal place.) Priority rule Mean Flow Time (Days) FCFS SOT STR DD

The following table contains information regarding jobs that are to be scheduled through one machine. Assume jobs are listed in order of arrival (i.e., A, then B, then C, etc.).

JOBPROCESSING
TIME (DAYS)DUE
DATE A7 20 B15 21 C1 16 D12 17 E11 15 F4 6 G5 12

a. What is the first-come, first-served (FCFS) schedule?
Job Flow Time