The following table contains information regarding jobs that are to be scheduled through one machine. Assume jobs are listed in order of arrival (i.e., A, then B, then C, etc.).
JOBPROCESSING
TIME (DAYS)DUE
DATE A7 20 B15 21 C1 16 D12 17 E11 15 F4 6 G5 12
a. What is the first-come, first-served (FCFS) schedule?
Job Flow Time