Tmp11
The Department of Transportation has found that a proposed highway project is not going to be completed before the end of the summer. They have asked the contractor to prepare cost figures to shorten the project by up to 4 weeks.
The following table shows the Crashing Costs for each activity. For example, if you needed to shorten Activity 1-2 by 1 week this would cost $12. If you needed to shorten the same activity by 2 weeks it would cost