value: 1.36 points Conceptual Question 19-11 Consider two projects that have the same activities… Consider two projects that have the same activities and the same dependencies. In the first project, the activity times are expected outcomes. The actual times will vary. In the second project, the activity times are always as expected. On average (in expectation), which project will be completed first? °The first °The second Cannot be determined

value: 1.36 points Conceptual Question 19-11 Consider two projects that have the same activities… Consider two projects that have the same activities and the same dependencies. In the first project, the activity times are expected outcomes. The actual times will vary. In the second project, the activity times are always as expected. On average (in expectation), which project will be completed first? °The first °The second Cannot be determined

 

Solution

There are two projects having the same activities and dependencies.