Which of the following is INCORRECT about lot sizing in Theory of Constrains systems? a process batch is the total lot size released to the shop a transfer batch is the quantity that moves from operations to operations Transfer batches can provide work centers with flexibility, such as, lot splitting and overlap. Original process batch is integral fractions of transfer batches

Which of the following is INCORRECT about lot sizing in Theory of Constrains systems?

a process batch is the total lot size released to the shop
a transfer batch is the quantity that moves from operations to operations
Transfer batches can provide work centers with flexibility, such as, lot splitting and overlap.
Original process batch is integral fractions of transfer batches

 

Solution

The correct answer is “Original process batch is integral fractions of transfer batches”.

The transfer batches are the integral fractions of process batch