Which of the following is not true about Six Sigma? A) In selecting projects for Six Sigma, managers should look for a clear link between the project and the company’s business priorities, as reflected in its strategic and annual operating plans. B) Projects should also be able to be completed within about three to six months. C) The CEO is often the champion for implementing Six Sigma. D) The biggest advantage of Six Sigma among organizations using the methodology is increased cost savings. E) Project team members are called “Green Belts.”

Which of the following is not true about Six Sigma?

A) In selecting projects for Six Sigma, managers should look for a clear link between the project and the company’s business priorities, as reflected in its strategic and annual operating plans.

B) Projects should also be able to be completed within about three to six months.

C) The CEO is often the champion for implementing Six Sigma.

D) The biggest advantage of Six Sigma among organizations using the methodology is increased cost savings.

E) Project

AllEscortAllEscort